Cybercab release date: every date Tesla gave, and what happened
Tesla has put a date on the Cybercab many times since October 2024. Here is each one, in order, next to what the record shows.
A Cybercab on display at Santana Row, San Jose. Photo: Dllu, CC BY-SA 4.0.
The short answer
The Cybercab is in production and carrying riders, but not yet in customers' hands. Tesla started production at Gigafactory Texas in 2026, began Cybercab rides in Austin on September 3, 2026, and opened invite-only orders on November 13, 2026 with a reported delivery estimate of December 2026. As of November 14, 2026, we found no report of a customer delivery.
| Unveiled | October 10, 2024 |
|---|---|
| Production started | 2026, Gigafactory Texas |
| First public rides | September 3, 2026, Austin |
| Personal orders | November 13, 2026, invitation only |
| Estimated delivery | December 2026 (reported) |
| Customer deliveries | None reported as of November 14, 2026 |
The timeline
Tesla's own quarterly reports, filed with the SEC, are the most reliable record of what the company promised and when. Press reports fill in what Elon Musk and other executives said out loud.
| Date | What Tesla said or did | Source |
|---|---|---|
| Oct 10, 2024 | Unveiled the Cybercab at its We, Robot event near Los Angeles. Musk said production would start in 2026 and the price would be under $30,000. | Reuters via Cyprus Mail reported |
| Jan 29, 2025 | "Preparation is underway for Cybercab lines at Gigafactory Texas with volume production planned for 2026." | Tesla Q4 2024 Update |
| Apr 22 and Jul 23, 2025 | Cybercab "scheduled for volume production starting in 2026." Factory status: construction. | Q1 2025; Q2 2025 |
| Oct 22, 2025 | Cybercab "on schedule for volume production starting in 2026." | Tesla Q3 2025 Update |
| Jan 28, 2026 | Production ramp "commencing 1H26." Factory status: tooling. | Tesla Q4 2025 Update |
| Feb 17, 2026 | First production Cybercab built in Texas. | Carscoops reported |
| Apr 22, 2026 | "We expect volume production of both Cybercab and the Tesla Semi this year." Factory status: pilot production. On that day's earnings call, Musk said, "We have just started production of Cybercab." | Tesla Q1 2026 Update; Electrek reported |
| Jul 22, 2026 | "Cybercab began production at Gigafactory Texas." Employees rode Cybercabs on the factory campus in July. The Cybercab was dropped from the list of products "on schedule for production starting in 2026." | Tesla Q2 2026 Update |
| Sep 3, 2026 | "We started providing Robotaxi rides using Cybercabs on September 3 in Austin." Public bookings in the Robotaxi app reportedly opened the next day. | Tesla Q3 2026 Update; Not a Tesla App reported |
| Oct 21, 2026 | Vehicle engineering chief Lars Moravy: "we're trying to get Cybercabs to customers by the end of this year, 2026." He added that all Cybercabs so far go to Tesla's own Robotaxi fleet. | Q3 2026 call transcript |
| Nov 13, 2026 | Invite-only orders for personal use opened. Estimated delivery shown: December 2026. | Electrek; Teslarati reported |
Production: on time, volume later
The 2024 promise was production in 2026, and that happened. Tesla's filings tracked the factory from construction in 2025 to tooling in January 2026, pilot production in April and production in July, when Tesla listed installed capacity of more than 125,000 Cybercabs a year.
The word that slipped is "volume." Every quarterly report from January 2025 to April 2026 promised volume production in 2026. In the July 2026 report, the sentence about products on schedule for 2026 kept the Tesla Semi and Megapack 3 and left the Cybercab out. On the October call, Moravy said customer Cybercabs would start small this year. Capacity is a ceiling, not an output figure, and Tesla has not published how many Cybercabs it has built.
First rides: Austin, September 2026
Cybercab rides for the public began in Austin in September 2026, inside Tesla's existing Robotaxi service area. Not a Tesla App reported that riders could pick a two-seat Cybercab or a four-seat Model Y in the app. By November 9, the same outlet reported more than 300 Cybercabs in Austin. On October 21, Tesla's finance chief said Cybercab rides were available only in Austin, and Tesla's head of AI software said the company would launch in Dallas the following month. How to ride, and what else runs in the city, is in our guide to robotaxis in Austin.
Customer orders and deliveries: not yet
Selling Cybercabs to individuals was not part of the 2024 pitch. Musk said on the October 2026 call that the vast majority of Cybercabs would be Tesla-owned and sold as transport as a service. Weeks later, on November 13, Tesla began inviting selected customers to order one for personal use. Press reports give the price as $29,990 before taxes, with a required $299 monthly subscription; the full cost is broken down on our Cybercab price page. Who can order, and the rules that come with it, are covered in can you buy a Cybercab.
December 2026 is an estimate on an order page, as reported, not a promise. Tesla has missed or moved dates before, as the volume production line shows. Until a customer posts a delivery or Tesla confirms one, treat the delivery date as unknown.
What to watch next
Three things will settle the open questions: Tesla's fourth-quarter 2026 report, which should say whether customer deliveries began; whether Cybercab rides launch in Dallas as Tesla said; and whether ordering opens beyond invitations. Our robotaxi data page tracks which cities have service. If you are weighing a Cybercab as a working car, running costs matter as much as the delivery date.
Questions
Has the Cybercab been released?
Partly. Tesla says it began production at Gigafactory Texas and started Robotaxi rides in Cybercabs in Austin on September 3, 2026. Personal orders opened by invitation on November 13, 2026. As of November 14, 2026, we found no report of a customer delivery.
When will Cybercab deliveries start?
The invite-only order page reportedly shows an estimated delivery of December 2026, and a Tesla executive said in October that Tesla is trying to reach customers by the end of 2026. Neither is a guaranteed date.
Did Tesla hit its 2026 production target?
Production started in 2026, as promised in 2024. Volume production is a different matter: in July 2026 Tesla dropped the Cybercab from its list of products on schedule for production in 2026, and Tesla has not published how many it has built.
Where can you ride a Cybercab?
Austin, through the Tesla Robotaxi app. Tesla's finance chief said on October 21, 2026 that Cybercab rides were available only in Austin. Press reports say Dallas Cybercab rides were scheduled for November 2026.
Sources
- Reuters via Cyprus Mail, October 11, 2024, on the We, Robot unveiling: cyprus-mail.com
- Tesla, Q3 2024 Update (Cybercab unveiled in October): sec.gov
- Tesla, Q4 2024 Update (volume production planned for 2026): sec.gov
- Tesla, Q1 2025 Update: sec.gov
- Tesla, Q2 2025 Update: sec.gov
- Tesla, Q3 2025 Update: sec.gov
- Tesla, Q4 2025 Update (ramp commencing 1H26): sec.gov
- Carscoops, February 18, 2026, on the first production Cybercab: carscoops.com
- Tesla, Q1 2026 Update (pilot production): sec.gov
- Electrek, April 23, 2026, on the start of production: electrek.co
- Tesla, Q2 2026 Update (production began; capacity over 125,000): sec.gov
- Tesla, Q3 2026 Update (Cybercab rides from September 3 in Austin): sec.gov
- Not a Tesla App, September 4, 2026, on public Cybercab bookings: notateslaapp.com
- Tesla Q3 2026 earnings call transcript, call held October 21, 2026: fool.com
- Not a Tesla App, November 9, 2026, on Cybercab count in Austin and Dallas plans: notateslaapp.com
- Electrek, November 13, 2026, on invite-only orders: electrek.co
- Teslarati, November 13, 2026, on December delivery estimates: teslarati.com